Lancashire Combined Fire Authority
Resources Committee
Meeting to be held on 29th March 2023
(Appendices 1 and 2 refer)
Contact for further information: Keith Mattinson - Director of Corporate Services
Tel: 01772 866804
Table 1Executive Summary and Recommendations
Executive Summary
The report sets out the current budget position in respect of the 2022/23 revenue and capital budgets. Recommendation
The Committee are requested to · note and endorse the current financial position · note the anticipated year end forecast overspend of between £1.5m and £1.75m.
|
Revenue Budget
The overall position at the end of January is an overspend of £1.3m, largely as a result of unfunded pay awards and inflationary pressures.
The year-to-date positions within individual departments are set out in Appendix 1, with major variances relating to non-pay spends and variances on the pay budget being shown separately in the table below: -
Table 2 Details of current budget position by department
Area |
Overspend/ (Under spend) |
Reason |
|
£’000 |
|
Fleet & Technical Services |
174 |
As reported in November, fuel has continued to overspend to £124k to date due to the sharp increase in fuel costs early this year. We are now seeing a slight reduction in trend as fuel prices start to decrease. An increase in mileage post pandemic has also attributed to increased costs. Repair costs are overspent to date by £70k due to inflationary pressures. It is projected both these areas will continue to overspend. |
Information Technology |
44 |
The overspend has reduced since November mainly due to timing of expenditure. Several software licences were prepaid earlier in the year levelling out in the latter part. There has been a general increase in costs, again reflecting inflationary pressures. |
Property |
583 |
Increased energy costs continue to cause significant overspend totalling £407k to date, however costs are not as severe as initially anticipated following the introduction of the business support scheme. Inflationary pressures continue to cause the maintenance costs to overspend, accounting for the balance of the overspend. |
Pensions |
(73) |
The underspend on pensions is due to fewer individuals retiring on ill health than budgeted. To date there is just one retirement due to ill health. |
Non DFM |
(585) |
The underspend is due to an increase in interest rates resulting in receiving an additional £400k interest to date. Also we have been awarded £102k VAT back on purchase of operational vehicles, having successfully challenged HMRC. |
Wholetime Pay |
857 |
Pay has significantly increased by £1m since November reporting due to the agreed 7% pay award for grey book, considerably higher than the budgeted 2%. Retirements and leavers are higher than anticipated, with this and a slight shortfall in recruit numbers being offset by increased overtime. |
On Call Pay |
5 |
This is broadly in line with budget having reflected the pay award. |
Support staff (less agency staff) |
110 |
The current position reflects the green book pay award, which was £1,925 per full time equivalent. This is significantly higher than the budgeted allowance of 2% and has increased costs over and above budget by approx. £400k by year end (please note at the time of writing the previous report we had assumed that the pay award would equate to approx. 5%, however based on our actual staff mix in year the actual costs are significantly higher at approx. 6.5%). This is partly offset by vacancies within the year, where recruitment has continued to be challenging, reflecting the employment market. And where we have continued to utilise temporary/agency staff to cover some key posts. |
Inflationary pressures and pay awards will continue to impact the budget for the remainder of the year, resulting in a year end overspend which we anticipate being approx. £1.5m to £1.75m. (We have not yet finalised this as we have moved onto a new finance system, provided by Lancashire County Council, which has resulted in some downtime and some challenges in extracting information from the system.)
As such we will need to utilise reserves to offset this. We currently hold £6.0m of general reserves, having agreed a minimum level of £3.75m, and as such we have sufficient reserves to meet this.
Capital Budget
Following the slippage previously agreed at the last Resources Committees the capital budget now stands at £3.3m. Spend to date is just £1.3m.as set out below, with further details in Appendix 2: -
Table 3 Details of current and forecast capital spend during the year by spend category
|
Revised Programme |
Spend to 31 January |
|
|
£m |
£m |
|
Operational vehicles |
0.9 |
- |
As reported previously whilst we have ordered a significant number of operational vehicle (13 pumping appliances, 2 Command Units and an ALP) lead times are such that we have not incurred any expenditure in the year to date. Whilst we have agreed a staged payment profile for these vehicles it appears increasingly unlikely that we will incur any such costs in year |
Support vehicles |
0.4 |
0.3 |
This budget allows for the replacement of various operational support vehicles, whilst some of these have already been delivered, the shortage of raw materials has affected both the timeframe for delivery and the cost of vehicles. Again it appears increasingly unlikely that we will spend all of the allocated funding in year. |
Operational Equipment |
0.3 |
0.1 |
Spend to date is attributable to the replacement of light portable pumps. We anticipate spending an additional £0.2m on CCTV for pumping appliances in-year. |
Building Modifications |
0.8 |
0.6 |
Spend to date is associated with:- · Enhanced facilities at Hyndburn fire stations, where works have been completed, at a cost of £0.2m · The replacement of drill towers, where Blackpool, Tarleton and Bolton le Sands have all been completed, at a cost of £0.4m |
IT systems |
0.9 |
0.3 |
Expenditure to date relates to a combination of replacement Vehicle Mounted Data Systems on appliances, the purchase of new Coverage Software, to aid with dynamic mobilizing, and the purchase of Incident Command Software. |
Total |
3.3 |
1.3 |
|
It is clear that we will not fully utilise the 22/23 capital programme and hence will need to slip funding into 23/24 to meet future costs, the extent of this will be reported as part of our year end capital outturn.
The costs to date will be met by revenue contributions, as reflect in the revenue budget year end forecast.
It is still worth highlighting that we continue to see significant cost increases across various supply chains, and in particular in construction projects and this will affect some of the capital projects as they progress through the procurement stage.
Business Risk
None
Environmental Impact
None.
Equality and Diversity Implications
None.
HR Implications
None.
Financial Implications
As set out in the report.
Local Government (Access to Information) Act 1985
List of Background Papers
Paper:
Date:
Contact:
Reason for inclusion in Part 2 if appropriate: N/A
Appendix 1
Table 4 Revenue Budget Monitoring Statement
Appendix 2
Table 5 Capital Budget Monitoring Statement